APUA Repairs Damaged Pigotts Transmission Tower, Temporary Power Interruptions Expected

Emergency work on a transmission tower in Pigotts prompted APUA to temporarily reroute sections of its electricity network Wednesday, disrupting power and reducing water production.
The Antigua Public Utilities Authority said the work involved replacing a damaged lightning arrester. Some communities lost electricity briefly as feeders were moved to other circuits to give repair crews safe access to the equipment.
APUA also sought help from selected businesses to limit pressure on the network by operating on standby generators during the repairs.
Water production was scaled back as well, with the Barnacle Point and Ffryes reverse osmosis plants taken out of operation because of their heavy electricity demands. Both plants are expected to resume production after the electrical work is finished.
Repairs were scheduled for completion before noon. APUA warned that another 15- to 20-minute outage could occur when the electricity network is restored to its regular configuration.
The authority thanked customers for cooperating and apologised for the disruption.
To support stories like these and help us continue delivering impactful journalism, call 268-772-4369 to learn how you can donate.
Advertise with the mоѕt vіѕіtеd nеwѕ ѕіtе іn Antigua!
We offer fully customizable and flexible digital marketing packages.
Contact us at [email protected]
Related News
The UWI Global Campus Alumni Office Marks a Decade of Excellence in Youth Development
LETTER: Nowhere Else to Turn
Minister Smith Urges Bipartisan Support for US Negotiations, Says Relationship Too Importa...